1871-1872 keeper selection and LH building Vol. 336

14
Indexed

14

Office of the Light House Engineer,

THIRTEENTH DISTRICT,

PORTLAND, OREGON, July 22, 1872

Chairman Light House Board,

Washington, D.C.

SIR: In reply to letter from your office of 12 July, I have to state that the lens and lantern for Cape Foulweather Light House arrived in San Francisco on the 19 May.

Very respectfully, Your obedient servant Henry M. Robert Maj. Of Eng’rs & L.H. Eng’r Thirteenth District.

Last edit over 6 years ago by lkarnatz

1870-73 Lighthouse Board Annual Reports

23
Indexed

23

1871. Aug. 30 (SIDE BAR) Yaquina rel payment of bills for survey of

From Engineer Secretary Major G. H. Elliot. To Major H. M. Robert Corps Engineers.

Sir:

The bill for survey of Yaquina reservation reffered to by your letter of the 18th instant can be paid if you con state on the face of the voucher, "ordered prior to July 1st, 1870"

Mileage cannot be paid to a civilian employe. In such cases actual necessary expenses, certified to by the employe are allowed.

Aug. 31.

From Engineer Secretary Major G. H. Elliot. To Major H. M. Robert Corps Engineers.

Sir:

Referring to your letter of the 19th instant, I have to inform you that Mr. J. A. Sesowrd has been entered on our books as Superintendent of Construction instead of draughtsman, and you may so rate him in your future returns.

Sept. 2 (SIDE BAR) Cape Foulweather L.H. - rel. completion

From Engineer Secretary Major G. H. Elliot To Major H. M. Robert Corps Engineers

Sir:

I have to inform you that J. T. Ames of Chicopee, Massachusetts, has a contract for making a first order lantern for the Cape Foulweather Light House and has agreed to have it finished ready to be sent to you, Care of Col. Williamson, San Francisco, by the 1st of January 1872.

Last edit almost 7 years ago by gkazebier
28
Indexed

28

1872.

(con)taining the 1st order lens, F. 240°, Cape Blanco 935,971: with lamps supplies, &c for Cape Foulweather Light House.

Apr. 18. From Engineer secretary Major G. H. Elliot. To Major H. M. Robert Corps Engineers.

Sir: In reply to your letter of the 2nd instant, I have to inform you that monthly reports of operations should be forwarded to the Board as soon after the close of the month as possible, so as to embody the month's actual operations.

Apr. 22. From Engineer Secretary Major G. H. Elliot. To Major H. M. Robert. Corps Engineers.

Sir: The U.S. Treasurer informs this office that your deposits with the Sub Treasury at San Francisco and with the 1st Nat'l Bank, Portland, Oregon, are not divided into Light House funds and Engineer funds.

It is important that this division be made at the bank and you will please attend to it that it be done as soon as practicable, and hereafter you will keep the accounts at the bank separate.

May 18 From Naval secretary C. S. Boggs. To Major H. M. Robert Corps Engineers.

Sir: Referring to your letter of the 2nd

(On the side bar) Cape Flattery L.H.

Referring to your letter of the 2nd

Last edit almost 7 years ago by gkazebier
29
Indexed

29

1872.

instant, you are authorized to enter into contraction written tenders for material, labor and transportation for Cape Foulweather Light House, requiring an answer within ten days and sending the tenders to the most reliable parties.

There is a clause in the appropriation bill which, if passed, will hold the appropriation good for two years from the time the site is obtained and jurisdiction ceded. You will be further informed on this point after the passage of the bill.

May 21.

From Naval Secretary C. S. Boggs. To Major H. M. Robert. Coprs Engineers.

Sir:

In reply to your letter of the 6th instant relative to Light House reservation at Yaquina, I have to say that the 20 acres referred to should be surveyed and permanent parks planted and report should be made as to whether these 20 acres will be sufficient for the purpose.

May 24.

From Naval Secretary Rear Adml. C. S. Boggs. To Major H. M. Robert. Corps Engineers.

Sir:

Referring to your letter of the 6th instant, relative to separation of funds, I have to say that as there is still some misunderstanding between the First National Bank at Portland and the [ Treasurer of the United States, you will please inform the Cashier of the Bank, that you should be mentioned in his reports as Light House Engineer.

Last edit almost 7 years ago by gkazebier
31
Indexed

31

1872 may be stated as "on or about". The form in regard to Cape Flattery will be forwarded at once giving the characteristic times of sound and interval.

July 12 From Engineer Secretary Major G.H. Elliot To Major H. M. Robert Corps Engineers Sir: Please inform this office whether the lens and lantern have been received for Cape Foulweather Light House.

July 23 From Engineer Secretary Major G.H. Elliot To Major H. M. Robert Corps Engineers Sir: Your letter of the 8th instant transmitting estimates for July 1872 is received. With a view of saving the General Appropriation for Repairs which always runs short at the end of the fiscal year, you will habitually (unless otherwise directed or unless there is some especial reason to the contrary, of which you will inform the Board) pay your office and other incidental expenses, from your Special Appropriations.

July 24 From Engineer Secretary Major G.H. Elliot To Major H.M. Robert Corps Engineers Sir: A Coast Survey chart of Columbia River No.1 has been this day sent you for

On Side: Cape Foulweather L.H. lens lantern, &c-rel-receipt of Office & incidental expenses to be paid from Special Appropriations Chart of Columbia River Sgub.

Last edit over 6 years ago by gkazebier