Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

2 revisions
Koliver at Feb 11, 2024 10:32 PM

60

-7-

covered by this contract must be kept open during the progress of
the work when so ordered by the engineer.

25. BENCH MARKS, STAKES, ETC.- All bench marks and all wit-
ness, side-slope and other survey stakes must be carefully preserved
by the contractor, and in case of their destruction or removal by
him or any of his employes, such stakes will be replaced by the
engineer at the contractor's expense.

26. CONTRACTOR'S FINANCIAL OBLIGATIONS.- The contractor shall promptly make payment to all persons supplying labor and materials in
the prosectution of the work. The contractors shall make such
financial arrangements that his employes will not be subject to
loss in securing their pay.