Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

3 revisions
Koliver at Feb 16, 2024 01:25 AM

63

upon the concrete base before
same shall have [received?] its
initial set shall be evenly spread
a single layer of 2½ inch [screwed?]
crushed rock and same hand
tamped into concrete base.

Immediately after the initial
set of the concrete shall have
taken place the high and loose 2½ inch
stones shall be removed leaving
depressions and projections when same was were
tamped into concrete.
The evening surface shall then
be applied.

63

upon the concrete base before
same shall have [received?] its
initial set shall be evenly spread
in a single layer of 2½ inch [??]
crushed rock and same hand
tamped into concrete base.

Immidiately after the initial
set of the concrete shall have
taken place the high and loose 2½ inch
stones shall be removed leaving
depressions and projections when same was were
tamped into concrete.
The evening surface shall then
be applied.