Sir. The estimated cost of the alteration of the fence at Mount Auburn will be as follows.
Estimate
Digging (already done) 1010 feet at 100?cts | $101.00 |
Settiang and taking down 215 " mew femce ..25 cts | 53.75 |
Carting do from the road to the rear [?gate] 6 " | 12..90. |
Loss of profit on 1600 feet of fence and extra | |
cost of building the remainder in the woods at 28 cts. | 448.00 |
The cost of the cedar posts. (they having been all cut | |
last winter) including wharfing and carting (1600 | |
feet of which will not be wanted) is. 98 cts pr.ft + | 1568.00 |
___ | $2183.65 |
The cost of the fence according to the new plan, will be 1.25 per lin\eal foot.
Respectfully yours Obt. Servt. (signed) Bryant & Blaisdell.