Office of the Light House Engineer
Thirteenth District,
Portland, Oregon.
December 17 1872
Chairman Light House
Board
Washington, D. C.
Sir:
I have the honor to
make a Report of
Operations for the
month of November,
1872.
Cape Foulweather
Lt Station, Ogn -
Received cargo of
Materials at Newport,
& hauled same to
L.H. Site.
Brick work finished to
within 2 1/2 feet of top
of tower. Floors laid.
Cement wash & white
wash finished on
outside, and 1 coat
white-wash on inside
walls. Carpenter work
finished on Tower &
oil-house. Parapet
plates put up. Continued
Painting wood & metal
work.
Probable Operations
for December-
Finish brick-work.
Put in new landing
& 2 flights of stairs.
Clear away scaffolding.
Commence putting
up Lantern &Lens if
new landing received.
Cape Hancock Lt
Station, W. T.
Purchased materials &
secured transportation
& men for work.
Probable Operations
in December.
Transport Men & Materials
to L.H. site. If weather
permits, & transportation
to landing on beach
to L.H. site can be
secured so as to cause
no delay, the station
walls will be built &
the Oil-House enclosed-
work. Put in new landing
& 2 flights of stairs. Clear
away scaffolding. Grading.
Commence putting up
Lantern & Lens if new
landing received.
Cape Hancock Lt
Station, W.T.
Purchased materials &
secured transportation
& men for work.
Probable Operations
in December.
Transport Men &
to Materials to L. H.
site. If weather permits,
& transportation ???
landing on beach to
L.H. site can be
secure so as to cause
no delay, the station
walls will be built &
the Oil-House enclosed-
| 27
Office of the Light House Engineer
Thirteenth District,
Portland, Oregon.
December 17 1872
Chairman Light House
Board
Washington, D. C.
Sir:
I have the honor to
make a Report of
Operations for the
month of November,
1872.
Cape Foulweather
Lt Station, Ogn -
Received cargo of
Materials at Newport,
& hauled same to
L.H. Site.
Brick work finished to
within 2 1/2 feet of top
of tower. Floors laid.
Cement wash & white
wash finished on
outside, and 1 coat
white-wash on inside
walls. Carpenter work
finished on Tower &
oil-house. Parapet
plates put up. Continued
Painting wood & metal
work.
Probable Operations for
December-Finish brick-
work. Put in new
landing & 2 flights of
stairs. Clear away
scaffolding. Commence
putting up Lantern &
Lens if new landing
received.
Cape Hancock Lt
Station, W. T.
Purchased materials &
secured transportation
& men for work.
Probable Operations
in December.
Transport Men & Materials
to L.H. site. If weather
permits, & transportation
to landing on beach
to L.H. site can be
secured so as to cause
no delay, the station
walls will be built &
the Oil-House enclosed-
work. Put in new landing
& 2 flights of stairs. Clear
away scaffolding. Grading.
Commence putting up
Lantern & Lens if new
landing received.
Cape Hancock Lt
Station, W.T.
Purchased materials &
secured transportation
& men for work.
Probable Operations
in December.
Transport Men &
to Materials to L. H.
site. If weather permits,
& transportation ???
landing on beach to
L.H. site can be
secure so as to cause
no delay, the station
walls will be built &
the Oil-House enclosed-
|