Report on the progress of work 3rd nov 1891
In the "Kinnear Park" The upper portion of the grounds
has been finished with the exeption of the
rustic structure and its immediate surroundings
We are now ready to put in the water pipe and
will have to call on the Water Dept to make our
connection with the system at the corner of Eples
and Bluff Sts. also request the Water Supdt
to tar-dip the pipe for us - say 1220 foot of 2" pipe
The walks and railings along the face of the
bluffs are well advanced - over 1000 feet
are completed and at present the entire
force is at work on the walks on the
lower portion of the park and in connection
with the I wish to mke the suggestion that
I be permitted to make a departure from
the plan so as to avoid a very heavy
fill and instead make a rustic bridge
and a pond for aquatic plants
(Explanations given on the plan)
We are now ready to proceed with the grading
of the "Denny Park"(team work) and I submit
a rough estimate of the cost of grading.
We have now got a supply of pots and
boxes in the nursery and the palnts are in-
creasing and prospering very favorable
Yours Respectfully Jas Taylor