Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

4 revisions
Seattle Municipal Archives at Dec 30, 2020 08:08 PM

990847_Page_4

Board of Public Works

W. V. RINEHART, CHAIRMAN
J. W. VAN BROCKLIN,
JESSE F. COCHRAN,
C. G. HEIFNER, SECRETARY
REGINALD H. THOMSON, CITY ENGINEER

DEPARTMENT OF
CITY ENGINEER
Seattle, Washington, Sept 22 1892

To Board of Public Works

Sir: Gentlemen: I find the facts set forth in the petition to be
true. The 14th St. Sewer is intended to end at 60 ft
South of Marion St, so that if any now be built it
would be better to complete this end of the systemn.
I estimate the cost of such proposed improvement as follows:


400 lineal feet of pipe laid @ 1 20 per foot 480.00
1 Manhole 50.00
1 Catch basin 50.00
1 Ventilator 20 --
Total $600.00
To Council
C G Heifner Sec

Very respectfull R. H. Thomson City Engr

990847_Page_4

Board of Public Works

W. V. RINEHART, CHAIRMAN
J. W. VAN BROCKLIN,
JESSE F. COCHRAN,
C. G. HEIFNER, SECRETARY
REGINALD H. THOMSON, CITY ENGINEER

DEPARTMENT OF
CITY ENGINEER
Seattle, Washington, Sept 22 1892

To Board of Public Works

Sir: Gentlemen: I find the facts set forth in the petition to be
true. The 14th St. Sewer is intended to end at 60 ft
South of Marion St, so that if any now be built it
would be better to complete this end of the systemn.
I estimate the cost of such proposed improvement as follows:


400 lineal feet of pipe laid @ 1 20 per foot 480.00
1 Manhole 50.00
1 Catch basin 50.00
1 Ventilator 20 --
Total $600.00
To Council
C G Heifner Sec

Very respectfull R. H. Thomson City Engr