Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

2 revisions
cgoldade at Mar 14, 2017 10:19 PM

10

Treasury Department
Office of Light-House Board.
Form 83

ESTIMATE OF COST PROPOSED WORKS.

Estimate for cementing cellar floors at Cape Foulweather Light Station, Oregon.

ESTIMATE

Price Amount

25 lbs. Portland cement 2.60 65.00
200 bush sand 25.00 50.00
10 days cement man 3.50 35.00
12 “ laborer 2.25 27.00
3 “ teamster and team 4.00 12.00
Superintendence, traveling expenses 40.00
Expenses of Tender 25.00

$254.00