Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

2 revisions
cgoldade at Mar 14, 2017 10:20 PM

12

Treasury Department
Office of Light-House Board.
Form 83

ESTIMATE OF COST PROPOSED WORKS.

Estimate for laying concrete foot walks around dwellings at Cape Foulweather Light Station, Oregon

ESTIMATE

Price Amount

10 lbs Portland Cement 2.60 26.00
250? bush sand & gravel .25 62.50
5 days cement man 3.5 17.50
6 “ laborer 2.25 13.50
2 “ teamster & team 4.00 8.00
Expenses of tender 10.00
Sundries 2.50

140.00