7
Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.
5 revisions | bluemermaid68 at Jan 14, 2017 03:28 AM | |
---|---|---|
7far obtained by this work are: the partial straightening of the channel, and the reducing of the limits of its movements; and the deepening of the water from about 8 feet to about 12 feet at low water. The project for the improvement contemplates extending the south jetty 1000 feet or more, and the building of a north jetty, some 3,000 feet in length. To carry out these works, an appropriation of about $500,000 will be needed. | 7 |